UNITIZED AND EFFICIENT INSTALLATION CONSTRUCTION TECHNOLOGY FOR LARGE-AREA CURVED HONEYCOMB ALUMINUM CEILING
Keywords:
Ceiling construction, Pre-assembly on the ground, Unitized installationAbstract
This paper proposes the "pre-assembly on the ground, unitized installation" construction technology to solve the ceiling construction problems of the first phase of the Hangzhou Convention and Exhibition Center project. It aims to improve construction efficiency and accuracy. By forming a professional surveying and mapping team to monitor the construction process throughout, we implemented structural optimization and precise control, effectively reducing the on-site labor demand by more than 40%, and reducing material loss and construction waste by more than 20%. This series of innovative measures not only ensures the project's construction period and quality goals, but also provides reliable technical references and experience references for the ceiling construction of large-scale exhibition buildings.References
[1] Shen Fanghua, Cai Hongwei, Wang Shuang, et al. Overview of Hangzhou Convention and Exhibition Center Project. Building Science, 2022, 38(05): 108-114.
[2] Yao Qiang, Wang Shuang, Cao Yun, et al. Analysis of architectural design points of Hangzhou Convention and Exhibition Center. Building Science, 2022, 38(05): 115-125.
Downloads
Published
2024-01-01
How to Cite
Yi Zhu, ZhiCheng Bai, YueQiang Cao, XiaoXia Zhao, YinGuang Wang, XiaoNing Feng. Unitized And Efficient Installation Construction Technology For Large-Area Curved Honeycomb Aluminum Ceiling. Journal of Trends in Applied Science and Advanced Technologies. 2024, 1(1): 1-5. DOI: https://doi.org/10.61784/asat3001.